Analysis of a super project of water supply / How will Hamadan’s drinking water supply route be paved?

According to the economic correspondent of Fars News Agency, half-finished projects are one of the major problems that the country’s vital infrastructure has faced in recent years.
One of the country’s infrastructure areas, which has a major share of half-finished projects in the country due to the performance of past governments, is the country’s water and sewage sector.
In this regard, the former deputy director of the Water and Wastewater Engineering Company of the 12th government, while explaining the status of half-finished projects of the Abfa industry, said: “Out of the 119 water supply projects in the country that were included in the budget of 1400, 28 projects have progressed above 80%. and 23% have progressed less than 20%. The rest of these plans have progress between 20 and 80 percent.”
Expressing the fact that 14,500 billion Tomans of office credit has been allocated to complete these 119 projects, this former official said: “In order to finish these 119 projects, we need 67,000 billion Tomans of money at today’s prices.”
Considering the number of half-finished projects in the past governments, the 13th government took over the executive activities with the attitude of completing the half-finished projects. In his speeches, the president repeatedly referred to the issue of completing half-finished projects and emphasized in some cases, as long as the unfinished projects are not put into operation, the new project will not be activated.
* Water supply to Hamedan is a project that remained untouched for 17 years
In this regard, one of the half-complete projects that was inherited by the popular government after 17 years, the water supply project to Hamedan from the dam Hall Is. The implementation of this 140-kilometer project started in 2006, but it progressed slowly in the past years and it was somehow stopped in the past 8 years.
Considering the importance of this dam in supplying drinking water to Hamedan city, after the 13th government took office, this project was included in the list of special emergency projects. In this regard, Mohammad Zabanakht, Deputy Minister of Water and Water Resources of the Ministry of Energy, in detailing the progress of this project, emphasized: “Everyone is aware of the financial limitations of the country in the current situation, but despite this, due to the high importance of the water supply project in Hamedan, the credits It was properly injected.”
This official emphasized: “The prolongation of the implementation time of this project had caused problems, which with the measures taken in the 13th government, this project came out of a complete stop and entered progress in the implementation of the work.”
* Details of the latest design of the first phase of water supply to Hamedan
According to the latest published official details of Hamedan water supply projects, recently a 16 km long alternative plan has been added to this project, based on which a dam water transfer line will be used. Hall to the dam Seaweed connects
This project has three pumping stations with a height of 576 meters, station number one and 2 are 220 meters each, and station number three has a pumping length of 136 meters.
In addition, five balance tanks with a capacity of 145,000 cubic meters have been placed in the plan, and the first tank station is 5,000 cubic meters, tank number 2 and 3 are 10,000 cubic meters each, tank number 4 is about 30,000 cubic meters and the treatment station The house transfers water to 2 tanks of 30,000 cubic meters, and a 30,000 cubic meter tank in the city of Hamedan.
* Opening Superproject Water supply to Hamedan in the next 2 to 3 weeks
According to Fars report, according to the latest news received from the Ministry of Energy, this project will be put into operation in the next 2-3 weeks, and the problem of drinking water for the people of Hamedan will be solved permanently with the opening of this project.
Ali Akbar Mehrabian, Minister of Energy, during his visit to this project, announced the mobilization of facilities and funds to complete this project and emphasized: Phase one Superproject Supplying drinking water to Hamedan can solve the water problem of this city and we are trying to put this project into operation in the next two to three weeks.
Considering this issue, it seems that in the coming days, we will witness the solution of Hamedan’s water supply problem with the completion of one of the half-finished projects.
end of Message/ T 19