The opening time of the remaining 10,000 residential units of Maskan Mehr has been determined – Tejaratnews


According to Tejarat News, Khalil Mohabbatekhah, CEO of New City of Fardis, said: The remaining 10,000 residential units of Mehr Housing will be ready to be delivered to applicants by the end of September.

Mohabbateh Khah added: We are trying to deliver these 10,000 units, which are in phases 8, 11, 5 and 9, to the applicants with 3 working shifts and securing credit.

He emphasized: the units will be delivered to the applicants as soon as they are ready.

Referring to the fact that each ready unit must have water, electricity and gas and landscaping has also been done in it, Mohabbateh added: Unlike previous years, the contractor does not hand over the unit to the applicant, but one of the technical colleagues of the new cities of Fardis company according to The checklist (checklist) that we prepared will deliver the units to the applicants.

He said: We will divide the remaining residential units into three parts. First, the plans that have more than 85 to 90 percent physical progress, which includes about 10 thousand units, and are part of the priority of opening and initial delivery.

Mohabbateh Khah added: The second category, which is more than 13 thousand units and has a physical progress of over 50%, is planned and under the condition of financing, the construction of these units will be completed by the end of the year, and the third category is units that have a 20% physical progress, which is about It is 20 thousand units that the completion of these projects is postponed to next year.

The CEO of New City of Fardis said: “In New City of Fardis, 84 thousand 148 housing units have been built since 2013, of which 29 thousand 821 units remain and about 54 thousand units have been handed over to applicants.”

According to Mohabbateh Khah, the 10,000 units that will be delivered to the applicants in September were supposed to be delivered to the applicants on March 28 of last year, but these units were not ready to be opened at that time and it is not known how they wanted them to be delivered to the applicants.

Source: Bazaar