Optical visit of Mandegar Shahid Modares High School resilience project – Mehr News Agency | Iran and world’s news

According to the Mehr news agency, the Minister of Education, Yousef Nouri, along with his deputy Mehrallah Rakhshani, Mehr, and the head of the country’s school renovation organization, visited the process of reviving and rehabilitating the historical school of Mandegar Shahid Modares High School before noon on Thursday, June 26, 1401.
In the heart of the ancient land of Iran, which has been known throughout history as the cradle of science, culture and art, there are many historical schools that show the value and credibility of knowledge and learning among the people of this land.
From military schools, Chahar Bagh school, Fakhrieh school and school جندی Shapur, which is thousands of years old, rather than schools رشدیهDar al-Fonun and Alborz, which were established as the first modern schools about 150 years ago, all tell the story of the country’s education.
In July 2005, a plan was approved by the Higher Education Council, according to which a number of eligible schools in the country were identified as “permanent schools” based on certain criteria. It was decided that these schools, in addition to preserving the identity and cultural heritage of the country, be included in the framework and cycle of education. About 100 permanent schools have been identified in the country so far.
Permanent schools are the identity of the education system or cultural identity of the country, the development and strengthening of which can facilitate the process of transfer of cultural heritage and education and as the first symbols of the education system and successful model of today’s schools in terms of architecture, technology, aesthetics and Both culturally and educationally.
One of the most prestigious and enduring schools in the south of the capital, in the heart of the historic city of Rey, is the “Enduring High School of Shahid Modarres”.
During his visit to Mandegar High School in Shahid Modarres, the Minister of Education, referring to the need to preserve the identity and historical aspects of the school building, stressed the need to accelerate the implementation of retrofitting operations and timely delivery of the project.
Shahid Modarres Mandegar High School is more than half a century old and many great men and celebrities of the country have studied in it, which is known as the third Mandegar School in Tehran after Dar Al-Fonun and Alborz schools. But let alone the vastness and magnificent architecture of this beautiful three-story building with colorful windows that dazzle the eyes of every viewer, we come across the memories and lasting memories of this high school that smells like the martyrs and brings to life the memories of the Islamic Revolution and holy defense. , A school with about 100 students and graduates التحصیلانش They have achieved a high position of martyrdom, which is another of its outstanding features.
The restoration operation of Mandegar Shahid Modarres High School began in June 2009 by the General Directorate of School Renovation in Tehran Province, with an emphasis on preserving the historical monuments and special architecture of the building. The renovation work of the school was carried out with special care and delicacy, and now it has reached its final days, so that, God willing, it will welcome the dear students at the beginning of the school year.
Mandegar Shahid Modares High School with a base of 5,400 square meters is located on a 9,000 square meter land and has 36 classrooms, 11 rooms for office work, and facilities such as library and reading room, prayer hall, meeting hall, computer room, laboratories. Chemistry, physics, biology, geology, classes dedicated to history and geography and the memorial of the martyrs of the holy defense.
The rehabilitation and rehabilitation operations of this school have 85% physical progress and will be completed by September of this year.